Ichthys Onshore Module Fireproofing

Client
STP&I
Construction site
Laem Chabang, Thailand
Period
2013-2016
Market
Energy
Country
Thailand
KAEFER services
Passive Fire Protection
Access Solutions

KAEFER was engaged by STP&I to complete fireproofing works and associated access services for modules as part of the Ichthys Onshore LNG Facilities Project.

Our Scope
  • All structural steel and pipe supports, which saw KAEFER install over 148,000m2 of Chartek products.
  • Approximately 500,000m3 of scaffolding was also erected as part of these works.

KAEFER completed over 500,000 manhours over the course of the works, with the contract successfully completed without any recordable incidents.

KAEFER
Delivering across full asset lifecycles, from construction to asset integrity, maintenance & shutdowns.