HomePTTGC Plant Turnaround Scaffolding PTTGC Plant Turnaround Scaffolding Client JGC Construction site Multiple sites, Thailand Period 2016-2017 Market Industrial Country Thailand KAEFER services Access Solutions KAEFER was engaged to provide scaffolding services as part of plant turnaround works. Our Scope 40,000m3 of scaffolding provided for turnaround works at three different plants (120,000m3 in total) KAEFER Delivering across full asset lifecycles, from construction to asset integrity, maintenance & shutdowns. Contact us now +61 8 9224 4600 Further Case Studies Arkema Symphony Project KAEFER was engaged to provide insulation and passive fire protection services for the new resin plant. Ichthys Onshore Module Fireproofing KAEFER was engaged to complete fireproofing works and associated access services for modules. Johan Castberg FPSO KAEFER was engaged to provide various insulation and cladding services for the Floating Production Storage and Offloading (FPSO) Vessel. Johan Sverdrup Phase II Architectural Works KAEFER was engaged for exterior outfitting services comprising fabrication and erection of architecture works. LNG Canada Pre-insulation Works KAEFER was engaged to undertake pre-insulation works on pipework associated with the jetty and run down lines for LNG plant modules. LNG Canada Tank Insulation KAEFER was engaged to undertake insulation & cladding services for a spherical tank. Long Son Petrochemicals Complex Insulation KAEFER was engaged for extensive insulation works for sphere tanks. MLNG Tank 7 KAEFER was engaged to provide insulation & cladding services associated with the LNG storage tank. MLNG Train 9 KAEFER was engaged to provide a range of services associated with the project. MOCD 2 Project KAEFER was engaged to provide refractory and insulation services.